headbg headbg
 
     
CAPRI Letter of 21st December 2009 to TBC

21st December 2009

 

Dear Mr Rider,

Application 08/01665/FUL

 

We have reviewed the additional information submitted by National Grid (NG) and our comments are below. The text in italics and marked ‘NG Letter’ is taken from NG’s letter to you dated 8th December 2009.

 

1.         Landscaping

The Inspectors reported that

 

“we feel strongly that the details of this proposal, in particular the quality of the landscaping, would fall far short of what should be expected from this statutory undertaker for this PRI development in a sensitive rural landscape” 1

 

Given this verdict, we do not understand why NG have perpetuated the wholesale shortcomings of the Appeal Site in their latest plans. Apart from issues around the unacceptability of an industrial site in open countryside, their proposal – both as originally stated and as currently amended - remains dependent on the same urban approach which they used at the Appeal Site, and which the Inspectors criticised because it was clear that there had been no involvement by a landscape architect: 2

 

You will also be aware that the Inspectors heavily criticised the use of bunds at the

Appeal Site, saying

 

“Indeed, the mounds themselves would be alien and intrusive features in the landscape and do little to help to assimilate the industrial development” 3

 

NG now propose the use of even larger bunds. Combined with a poor choice of tree

and shrub species, and technically difficult - if not unachievable - ways of trying to

secure rapid establishment for screening purposes, these current proposals will

accentuate the intrusion of this large installation into the countryside rather than

mitigate its impact.

 

NG have paid lip service to countryside conservation objectives by their simplistic

and wholly inadequate approach to dealing with the special character of the Application Site. Comparison of the detailed plans for Tirley with those rejected for the Appeal Site shows the presentation of an almost identical approach which will result in a grossly intrusive and alien feature in the local landscape which will be evident for very many years. This industrial development would never merge into the local scene and would always remain an eyesore.

 

 

2. Lighting: Telescopic lighting standards

“The possibility of using telescopic lighting columns has been considered. Whilst such lighting arrangements can be employed in other locations, we would not be able to use standard units (incorporating electric motor drive units) in a controlled gas site.”

NG Letter

 

NG claim that they would not be able to use ‘standard’ units (incorporating electric motor drive units) but they do not give a reason. However, they do not totally exclude the possibility of using telescopic lighting columns. In the absence of a proper explanation, we do not consider that our comments have been addressed.

 

 

3. Hedgerow

The view is being advanced by NG that the hedgerow will afford a visual barrier through which drivers using the B4213 would find it difficult, if not impossible, to see the proposed PRI. NG say:

 

“The view [of the lighting columns] would be transitory, as the relocated hedge and proposed roadside mound with planting would close these views for most drivers using the road.”

NG Letter

 

We dispute this statement.

 

3.a) NG limit their statement to lighting columns. There will also be 12 exhaust flues and these will not only be higher than the lighting columns but will also have a larger diameter, and consequently will be more visible, and intrusive, than the lighting columns.

 

3.b) For approximately six months of the year the hedgerow is without leaf and consists only of a random criss-cross of twigs and branches. When a person standing on the road looks at - and through - this patchwork, his eyes focus on the twigs in the  foreground and he is less aware of the background. However, when a driver moves along the road in a car, his eyes and brain function differently. The twigs and branches move past him at a speed which his eyes do not have the capacity to resolve and he therefore focuses on the background. Although at no time does he have a whole and uninterrupted view of the background, the speed of the interruption is so fast and so varied that his brain extrapolates and interpolates the missing data and he is left with an apparently near-uninterrupted of the background.

 

(This phenomenon is similar to flashing a series of cards, each of which has a picture which is taken slightly later in time to its predecessor; the effect is to show movement4. In the case of the hedgerow, a better parallel would be where each card shows a picture of the background, but with each picture being slightly incomplete in a different way from every other picture. The effect for the viewer – the driver – is the removal of the hedgerow as an effective visual barrier.)

 

3.c) The construction of a bund 1 metre high for a short length to the west of the entrance to the site from the B4213 will be largely irrelevant in summer when the hedgerow is in leaf and, in winter, when the hedgerow does not offer an effective visual barrier, will serve to bring closer to the public the artificiality of the construction. Given that the height is only 1m - and that for just 50 metres (or 2 seconds for the passing motorist) it is unlikely to be high enough to achieve its primary purpose of preventing views into the PRI .

 

3.d) The hedgerow along virtually the whole of the north side of the B4213 is high and has been left untended for many years. The owner of the hedgerow will be free to lay or otherwise reduce the height of the hedge at any time and there could then be an uninterrupted view of the lighting columns and vent stacks of the PRI.

 

 

4. Site Option 16

 

4.a)      Economic and efficient

“However, as the Inspectors made clear in their report on the Corse PRI appeal, regard must be had to National Grid's statutory obligation to develop its gas transport infrastructure in an economic and efficient manner. The additional costs of alternative schemes are therefore a material planning consideration.”

NG Letter

 

NG appear to suggest that the statutory duty laid upon them to construct an infrastructure in an economic and efficient manner requires that they exclude Site 16 as a possible choice.

 

It should be remembered that the Inspectors severely criticised NG for failing to examine the land beyond a radius of 1 km from the Appeal Site. It follows from this that the Inspectors did not consider that the additional cost inherent in building a PRI

at up to 10km from the AGI was necessarily a bar to siting a PRI at Site 16 or indeed at any location within that 10km circle. It follows from this that a full and proper evaluation should be made of the Site 16 option and that the additional cost implicit in the selection of Site 16 is not a material consideration.

 

4.b)      Proximity to AGI

“the Inspectors acknowledged that the consideration of alternatives has to be made in the context of certain constraints, including the technical objective of locating the PRI and the AGI as close together as possible.”

NG Letter

 

This is not a valid argument for excluding the possibility of Site 16. Whilst technically it may be desirable to co-locate these two facilities, the Inspectors severely criticised NG for not examining the possibility of locating the PRI up to 10 kms distant from the AGI5; that is, separating them by as much as 10km. If the Inspectors had accepted the argument that the two facilities should be located as close to each other as possible, they would not have required NG to examine this enlarged area, nor indeed would they have had an argument for refusing the appeal because the enlarged area had not been researched.

 

5.         Need to consider alternatives

Site 16

 

“It is evident that the current proposals have addressed the concerns expressed by the Inspectors and that the need for the development outweighs any harm that may be caused. In those circumstances, it is unnecessary to determine whether there is any better alternative to the application proposals.”

NG Letter

 

It is for the reasons cited by NG that they have undertaken no proper evaluation of Site 16. Their reluctance to consider this Site, first evidenced by the surprise of their representatives when they were invited to walk to the Site during the site visit undertaken by the Planning Officers and CAPRI, and further confirmed by the limited assessment which they have since produced, is obvious. NG, having determined that there is no need to consider Site 16 as a candidate site because the choice of that site would breach their ‘economic and efficient’ duty, have given it no proper

consideration.

 

The current proposals do not address the concerns of the Inspectors and, as we have previously stated, the proposal does not comply with either the relevant local or national planning policies.

 

 

 

5. Land area

We wish also to bring to your attention the fact that NG have issued a Compulsory Purchase Order for an area of land greatly in excess of that required for the PRI or its associated landscaping. Some additional land may be needed during the construction phase for the temporary storage of tools and equipment, but NG have declined to give an assurance that that additional land would be returned to the original owner when construction was complete.

 

We are accordingly concerned that NG may therefore view this site as being suitable

for further but as yet unannounced development.

 

 

6. Conclusion

We conclude by repeating our previous claim that, whatever minor cosmetic improvements are made to the proposal, granting permission to build a PRI at this location would be wholly unjustified because it is the wrong location, and is an industrial installation which is contrary to the Development Plan.

 

Yours sincerely,

 

P. M. McMurtrie

Chairman

 

1 Inspectors’ Report, para 8.111

2 Inspectors’ Report, para 8.62

3 Inspectors’ Report, para 8.59

4 Pictures appearing at a rate of 16 per second give an impression of relatively fluid motion.. A ¼ inch diameter twig would interrupt the view of a passing motorist for approximately 1/4,000 of a second – that is, would effectively be invisible.

5 “We accept that finding a suitable alternative site for the PRI would not be an easy task but we have sympathy with the argument that the consideration of an area of search that looks at only 1% of the potential area does not signify a serious and concerted effort and it should be given little credence. “

Inspectors’ Report, para 8.69

 

 
© CAPRI 2012